File #: 11-379    Version: 1 Name: Airport Semi-Annual Response to 2007 Adopted Budget Amendment 1B027 on Airport Capital Improvement Projects and Approval to Rescind Amendment 1B027
Type: Action Report Status: Rejected
File created: 8/30/2011 In control: County Clerk
On agenda: Final action: 9/29/2011
Title: From the Director, Department of Transportation and Public Works, and the Airport Director submitting an informational report on the status of all currently authorized Airport Capital Improvement Projects and requesting that 2007 Budget Amendment 1B027 be hereby rescinded and the requirement for the semi-annual report be eliminated. (Referred to the Committees on Transportation, Public Works, and Transit and Finance and Audit.)
Attachments: 1. REPORT, 2. RESOLUTION, 3. FISCAL NOTE, 4. ATTACHMENT, 5. CB Resolution TPWT 10-404, 6. Audio TPWT 09/14/11
Related files: 12-351, 12-766, 12-887, 13-291, 13-668
Title
From the Director, Department of Transportation and Public Works, and the Airport Director submitting an informational report on the status of all currently authorized Airport Capital Improvement Projects and requesting that 2007 Budget Amendment 1B027 be hereby rescinded and the requirement for the semi-annual report be eliminated. (Referred to the Committees on Transportation, Public Works, and Transit and Finance and Audit.)

Body
POLICY
County Board approval is required to terminate 2007 adopted budget Amendment 1B027 on Airport Capital Improvement Projects.
BACKGROUND
Based on discussions held during the Finance Committee’s review of the Airport’s Capital Improvement Budget in late 2006, the 2007 budget included Amendment 1B027 relating to the Airport Capital Improvement Projects. The directive from the amendment includes that:
“The Airport Director shall submit quarterly reports to the Committees on Finance and Audit and Transportation and Public Works on the status of all currently authorized Capital Improvement Projects. In a form pre-approved by the DAS Capital Finance Manager, County Board staff and Director of Audits, the report shall provide the following information for each authorized Capital Improvement Project:
• Date of initial County Board approval
• Brief description of scope of project
• Estimated completion date
• Expenditures and revenues summary, including reconciliation of each revenue source (e.g. Passenger Facility Charges, Airport Reserve, Bonds and Miscellaneous Revenue) and amount of committed funds for each.
• Date, purpose and amount of any approved appropriation transfers
The Finance Committee later recommended that the presentation of this capital improvement report be adjusted to biannual rather than quarterly as originally directed. Semi-annual reports have since been provided.
Attached is the first semi-annual report for 2011, which indicates the expenditure and revenue summaries of the Airport’s active Capital Impro...