From Engberg Anderson providing a presentation on the baggage claim remodeling project at General Mitchell International Airport (GMIA). (INFORMATIONAL ONLY UNLESS OTHERWISE DIRECTED BY THE COMMITTEE)
Body
POLICY
Informational
BACKGROUND
The Airport's 2011 Capital Budget included $5,436,000 for design of a remodeled baggage claim building. The project included new baggage claim carousels, new mechanical, electrical, restrooms, and lighting. Also the project included new curb-fronts and a canopy to cover much of the baggage claim roadway protecting passengers from the weather.
Construction is anticipated to start in early 2012 and last approximately 16 months.
Engberg Anderson will make a brief presentation on design efforts to date.
Prepared by: C. Barry Bateman, Airport Director
Approved by:
_______________________ ________________________
Jack Takerian, Director C. Barry Bateman
Transportation and Public Works Airport Director
Cc: Lee Holloway, County Board Chairman
H:\Private\Clerk Typist\Aa01\TPW&T 11\Sept 2011\REPORT - INFO - Engberg Anderson Presentation_baggage claim remodel.doc